Susquehanna Township, Juniata County
- County
- Juniata County
- Citation
- 10.a.i & 10.a.iv (2024) [pg. 14, contact Township through "County Directory" for access]
- Date of data entry
- Sep 11, 2025
- Source document
- View the ordinance (opens in a new tab)
Relevant text
[An application for a permit for a Principal Solar Energy Facility shall document compliance with the requirements of this ordinance and shall include, among other things, the following:]
"I. A detailed narrative describing the proposed Principal Solar Energy Facility, including an overview of the project; the project location; agreements with landowners to allow the Principal Solar Energy Facility to be constructed and operated on their property; the approximate generating capacity of the Principal Solar Energy Facility; the location and distance to the point of interconnection with the power grid, the means of connecting to the power grid; and the approximate number, representative types and heights of Solar Related Equipment to be installed;"
"iv. Proof of landowner consent to allow the proposed Principal Solar Energy Facility to be constructed and operated together with an acknowledgment of the landowner's obligations under this ordinance, including providing Susquehanna Township and its employees, representatives, agents and contractors with reasonable access to the Principal Solar Energy Facility and the right of Susquehanna Township to enter the Principal Solar Energy Facility to conduct decommissioning activities if not carried out by the Owner of the Principal Solar Energy Facility in accordance with this ordinance;"