South Huntingdon 2nd Township, Westmoreland County
- County
- Westmoreland County
- Citation
- 9 (2024) [pg. 5-6]
- Date of data entry
- Sep 11, 2024
- Source document
- View the ordinance (opens in a new tab)
Relevant text
"A. The Facility Owner and Operator shall, at their expense, complete decommissioning of the Solar Electric Energy Facility or individual Solar Electric System within twelve (12) months after the end of the useful life of such Facility or System. A Solar Electric Energy Facility or System will be presumed to be at the end of its useful life if no electricity is generated for a continuous period of twelve (12) months."
"C. Decommissioning shall include removal of all Solar Electric Energy Systems, buildings, cabling, solar panels, electrical components, roads, foundations, and any other associated facilities.
D. Disturbed earth shall be graded and re-seeded unless the landowner request in writing that the access roads or other land surface areas not be restored. ”