Pine Township, Allegheny County
- County
- Allegheny County
- Citation
- 84-84.R; 84-84.S.3; 84-84.S.4 (2024)
- Date of data entry
- Aug 17, 2024
- Source document
- View the ordinance (opens in a new tab)
Relevant text
"R. At the time of issuance of the permit for the construction of the large solar energy facility, the owner shall provide financial security in form and amount acceptable to the Township to secure the expense of dismantling and removing said structures."
"(3) The large solar energy facility and all related equipment shall be removed within 12 months of the date of discontinuation or abandonment or upon the determination of the useful life of the solar system.
(4) For ground-mounted and building-mounted systems, removal includes removal of all structural and electrical parts of the ground- or building-mounted system and any associated facilities or equipment and removal of all net metering equipment."