Palmer Township, Northampton County
- County
- Northampton County
- Citation
- 190-972.Q.5 & 190-972.R.5 (2023)
- Date of data entry
- Nov 16, 2024
- Source document
- View the ordinance (opens in a new tab)
Relevant text
"5. If a ground mounted solar energy system is removed, any earth disturbance as a result of the removal of the ground mounted solar energy system must be graded and re-seeded. In addition, any underground utilities shall be removed."
"2. The solar energy system owner shall then have 12 months in which to dismantle and remove the solar energy system including all solar related equipment or appurtenances related thereto, including, but not limited to, buildings, cabling, electrical components, roads, foundations, and other associated facilities from the property. If the owner fails to dismantle and/or remove the solar energy system within the established timeframes, the Township may complete the decommissioning at the owner's expense."