Clarion County
- County
- Clarion County
- Citation
- 3.A.10.a & 3.A.10.b (2021) [pg. 3-4]
- Date of data entry
- May 23, 2024
- Source document
- View the ordinance (opens in a new tab)
Relevant text
“a) The PSES owner is required to notify the County upon cessation or abandonment of the operation. The PSES shall be presumed to be discontinued or abandoned if no electricity is generated by such system for a period of twelve (12) continuous months.
b) The PSES owner shall then have twelve (12) months in which to dismantle and remove the PSES including all solar related equipment or appurtenances related thereto, including but not limited to buildings, cabling, electrical components, roads, foundations and other associated facilities from the property. If the owner fails to dismantle and/or remove the PSES within the established timeframes, the County may complete the decommissioning at the owner's expense.” See "Financial assurance..." for further information.